Time:2020年04月28日 人气: 来源:本站原创
The annual output of castings will increase, and the 20-ton electric arc furnace has arrived and will be installed in June.
① The 5-ton electric furnace runs 4 heats per day, enabling an annual increase of 3,000 tons in casting output.
② Affected by the pandemic, the 20-ton electric furnace is expected to be delivered and installed in June. Upon commissioning, all 5 electric furnaces will operate simultaneously, capable of casting heavy pump components weighing up to 30 tons. The entire process—from casting, machining, assembly to testing—for pumps with a capacity of 60,000 m³/h can be completed in-house.